Recent updates to California law impose new limitations on retainage for private construction projects. Under the updated California Prompt Payment Act, retainage on private works is now capped at 5 percent of the contract price.1
This statutory cap carries meaningful enforcement mechanisms. If an owner or contractor withholds retainage in excess of the permitted amount or otherwise fails to make timely payment of retainage, the withholding party may be subject to:
- a 2 percent per month penalty on the improperly withheld amount<2
- liability for attorneys' fees and costs of the prevailing party in any enforcement action3
Importantly, the statute expressly provides that the 5 percent retainage cap cannot be waived by contract.4 Any contractual provision allowing for retainage in excess of 5 percent is unenforceable, regardless of the parties' agreement.