Share on LinkedInShare on LinkedIn

ARTICLE · 01 AUGUST 2018

Banker & Tradesman Publishes "SJC Ruling Brings Law In Line With Industry Practices"

Since at least 1940, parties to construction contracts have been held to high standards of showing "complete and strict performance of all [of the construction contract's] terms."

United StatesReal Estate and Construction

Since at least 1940, parties to construction contracts have been held to high standards of showing "complete and strict performance of all [of the construction contract's] terms." This has historically turned otherwise straightforward disputes over payment into battles where the parties could point to any performance failure as a basis to avoid liability. It also impacted construction projects in the context of termination where any breach of a construction contract was a default that could lead to termination. The result was that owners and upstream contractors had significant leverage to enforce their contracts.

That rule changed on June 13 when the Commonwealth's Supreme Judicial Court issued its decision in G4S Technology LLC v. Massachusetts Technology Park Corporation, in which a design builder on a publicly funded broadband installation project had its breach of contract claims dismissed due to evidence of having submitted false payment certifications. The SJC

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from