On Nov. 16, 2024, the Arlington County Board adopted several
policies designed to lay the groundwork for office-residential
projects in Arlington County, Virginia.
The Board adopted
zoning ordinance
amendments for “adaptive reuse” projects that
involve changing a building's use from office to hotel or
residential with only nominal changes in density and/or height. The
amendments establish an expedited entitlements process for adaptive
reuse projects. According to a
staff presentation from the Nov. 16 Board meeting, the
intent of the amendments is to establish a 120- to 150-day review
process for adaptive reuse projects. Prior to Board adoption of the
adaptive reuse zoning ordinance amendments, board approval of an
adaptive reuse project could take more than 12 months.