Are Liquidated Damages Down The Drain In California?

Liquidated damages can provide parties added incentive to perform all types of contracts, including commercial real estate contracts. But are they enforceable in California?

United StatesReal Estate and Construction

Liquidated damages can provide parties added incentive to perform all types of contracts, including commercial real estate contracts. But are they enforceable in California? The short answer is that they're presumed to be enforceable as long as they're not a penalty.

Historically, liquidated-damages provisions were disfavored because courts considered them penalty clauses. However, in 1977, California changed the policy of presumptive invalidity of liquidated damages provisions with a policy of presumptive validity in commercial, non-consumer contracts. Generally, that means that a provision in a contract liquidating damages for a breach is valid unless the party challenging the provision establishes that it was unreasonable under the circumstances that existed at the time the contract was made.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from