The Washington Supreme Court’s recent decision in Polinder v. Brand Insulations, Inc., No. 102782-6 (Wash. Apr. 30, 2026), provides clarifications on how the construction statute of repose applies to contractors in asbestos litigation. By resolving conflicting appellate decisions, the Court established a more precise framework for evaluating when a contractor’s historical installation work is shielded from liability and when it is not.
Background: The Construction Statute of Repose
In Washington, the construction statute of repose, Wash. Rev. Code § 4.16.300 (2026), applies to claims arising from a person having "constructed, altered or repaired any improvement upon real property.” Wash. Rev. Code § 4.16.310 (2026) dictates that such claims must accrue within six years of the substantial completion of construction.