Action Not Barred By Six-Month Contractual Limitation Of Time

In the recent case of JC Ryan EBCO/H & G, LLC v. Lipsky Enterprises, Inc., 2010 NY Slip Op 8073, 2010 N.Y. App. Div. LEXIS 8280 (November 9, 2010) the Appellate Division, Second Department upheld a trial court’s denial of a motion to dismiss, which motion was based upon a six month contractual limitation of time.

United StatesReal Estate and Construction
Robert Mark Wasko
Robert Mark Wasko

Originally published in  STA Subcontractors News, January 2011.

In the recent case of JC Ryan EBCO/H & G, LLC v. Lipsky Enterprises, Inc., 2010 NY Slip Op 8073, 2010 N.Y. App. Div. LEXIS 8280 (November 9, 2010) the Appellate Division, Second Department upheld a trial court's denial of a motion to dismiss, which motion was based upon a six month contractual limitation of time. The basis of the decision was that there was a conflict between the contractual limitations period and a pay-when-paid clause in the contract.

Parties to a contract are generally free to shorten statutory limitation periods in which to commence a lawsuit, provided that the shortened limitation is not found in a contract of adhesion, is not the product of overreaching, or is not an unreasonably short period. Although the statute of limitations for a breach of contract action is six years (CPLR 213[2]), contractual reductions of time to one year or even six months have generally been upheld by