ARTICLE · 16 NOVEMBER 2020

Narrow Appellate Court Ruling Excuses Project Contractor From Quitting Due To Partially Withheld Payments

Every party to a contract must uphold the duty of good faith and fair dealing. But there is no free-floating duty under Washington law: the parties' respective obligations must be tied to a particular contract provision.

United StatesLitigation, Mediation & Arbitration

Every party to a contract must uphold the duty of good faith and fair dealing. But there is no free-floating duty under Washington law: the parties' respective obligations must be tied to a particular contract provision. Division One of the Washington Court of Appeals recently determined that a project owner's continued underpayment, if material, excused a general contractor from performance based on the duty of good faith and fair dealing. Materiality of the alleged breach remains the key to excusing performance.

In Lake Hills Investments, LLC v. Rushforth Construction Co., Inc., the court of appeals examined whether an owner's continued underpayment could excuse a contractor from quitting the project. The owner (Lake Hills) had partially withheld payments from the contractor (AP) over several months on a construction project in Bellevue. The court of appeals considered whether such prior underpayment by Lake Hills could excuse AP's decision to leave the job. With a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from