In Gilchrist Constr. Co., LLC v. Louisiana Dep't of
Trans. and Dev., a Louisiana appellate court recently
confirmed that a contractor was able to demonstrate delay damages
due to a critical path delay based on increased work requirements
even though the contractor was ultimately able to finish the
project ahead of schedule. The project involved the widening of an
interstate highway for the Louisiana Department of Transportation
and Development. Gilchrist, the contractor, finished the project
ahead of schedule and was paid the contract price, including
additional compensation for change orders and an early completion
bonus. The principal issue was the recoverability of delay costs
for a dispute concerning the scope of work and what the contractor
alleged to be the state's gross miscalculation of the quantity
of embankment required for the project. Gilchrist alleged that, but
for the state's gross miscalculation, it would have bid 180
more days. The trial court rendered