Unique Facts Entitle Contractor to Recover Under Mutual Mistake Theory

August 1, 2019, the Armed Services Board of Contract Appeals (ASBCA) held that the Air Force should bear the costs associated with a mutual mistake of fact in a contract between DynCorp International

United StatesGovernment, Public Sector

To obtain relief pursuant to the mutual mistake of fact theory, contractors must demonstrate that both parties believed a mistaken fact to be true.

The contractor must further show that—no matter the size or scope—the mistake had a “material” adverse impact on the parties’ bargain.

When neither party has assumed the risk of a latent mistake of fact, the Board will allocate the risk to the more culpable party.

On August 1, 2019, the Armed Services Board of Contract Appeals (ASBCA) held that the Air Force should bear the costs associated with a mutual mistake of fact in a contract between DynCorp International LLC (DynCorp) and the Air Force. This result suggests that the theory of mutual mistake of fact remains a viable one for contractors to consider and pursue.