Jenner & Block’s London office has built a powerful reputation for representing clients in their...

View firm profile
Explore more from Jenner & Block LLP

Government contractors are often faced with the dilemma of their proposed key personnel becoming unavailable for contract performance, through no fault of their own,...

United StatesGovernment, Public Sector

Government contractors are often faced with the dilemma of their proposed key personnel becoming unavailable for contract performance, through no fault of their own, at a point after proposal submission but prior to contract award. In such cases, the Government Accountability Office (GAO) has espoused a rule that obligates offerors to advise contracting agencies of material changes in proposed staffing, even after proposal submission. See, e.g., AttainX, Inc., B-419306, B-419306.2, Jan. 12, 2021, 2021 CPD ¶ 21. But a recent decision by the Court of Federal Claims (CoFC) challenges this rule, casting doubt on its basis in law or regulation.

In Golden IT, LLC v. United States, No. 21-1966C, __ Fed. Cl.__, 2022 WL 334369 (Feb. 4, 2022), the awardee Spatial Front, Inc. (SFI) had proposed an individual (identified in the decision as "Mr. JH") as a key personnel. At the time of submission, Mr. JH was an SFI employee, but departed the company prior to contract award.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from