Congress enacted the Buy American Act ("BAA") during
the Great Depression, in order to protect American industry from
foreign competition on federal procurement contracts. While the BAA
is simplistic in its policy goal of promoting domestic purchasing,
government contractors and subcontractors are often faced with
complex and confusing rules for compliance.
The operative language of the BAA provides:
Only unmanufactured articles, materials, and supplies that have
been mined or produced in the United States, and only manufactured
articles, materials, and supplies that have been manufactured in
the United States substantially all from articles, materials, or
supplies mined, produced, or manufactured in the United States,
shall be acquired for public use unless the head of the department
or independent establishment concerned determines their acquisition
to be inconsistent with the public interest or their cost to be
unreasonable1.