ARTICLE · 18 JANUARY 2018

Snowmen In August: Strict Compliance And Government Waiver Of Contract Requirements

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

The Government "can engage a contractor to make snowmen in August, if [it spells] it out clearly [in a contract]." Rixon Electronics, Inc. v. United States, 536 F.2d 1345, 1351 (Ct. Cl. 1976).

United StatesGovernment, Public Sector

The Government "can engage a contractor to make snowmen in August, if [it spells] it out clearly [in a contract]." Rixon Electronics, Inc. v. United States, 536 F.2d 1345, 1351 (Ct. Cl. 1976). And the contractor generally must make the snowman as the contract directs, even if the contractor can think of a better way to get the work done. A recent decision of the Armed Services Board of Contract Appeals (ASBCA) provides a useful reminder, both of the ordinary obligation for contractors to comply with all requirements of their government contracts, and of an important limit to that obligation.

The Facts

American West Construction, LLC, ASBCA No. 61094 involved a fixed price order issued by the Army Corps of Engineers for construction of permanent bridges over irrigation canals near the border between Texas and Mexico. To permit construction of one of the permanent bridges, the order called for construction of two temporary bridges, which were to be dismantled and