Raytheon Co. v. U.S. – The High Hurdle To Challenging Agency Corrective Action

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

The circuit's decision serves as an important reminder of the high hurdle that an unsatisfied litigant at GAO must overcome to overturn agency corrective action.

United StatesGovernment, Public Sector

On October 23, 2015, the Federal Circuit affirmed1 a decision from Judge Sweeney of the Court of Federal Claims rejecting Raytheon Company's challenge to the Air Force's decision to take corrective action following outcome prediction by GAO. The circuit's decision serves as an important reminder of the high hurdle that an unsatisfied litigant at GAO must overcome to overturn agency corrective action.

During the subject procurement, Raytheon prevailed over two competitors, Northrop Grumman Systems Corporation and Lockheed Martin Corporation, in a competition for a $71.8 million contract to provide equipment and services for the Air Force's new long-range radar program. Northrop and Lockheed filed protests at GAO, which, following a hearing, conducted outcome prediction ADR. GAO informed the parties that it was prepared to issue a decision sustaining the protest in part on the basis that the Air Force's discussions with Northrop were misleading and unequal as compared