Now Or Never – Protecting Your Right To Recover Costs Caused By The Government Shutdown

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

Now that the government shutdown has ended, contractors must quickly assess whether and how to recover any additional costs that were caused by the shutdown.

United StatesGovernment, Public Sector

Now that the government shutdown has ended, contractors must quickly assess whether and how to recover any additional costs that were caused by the shutdown. The clock is ticking and any unjustified delay may result in a contractor being denied recovery of otherwise recoverable costs.

It is without question that the government shutdown materially impacted government contractors in a myriad of ways. Some contractors received direct suspension of work orders from their contracting officers. Others were unable to deliver goods or services due to the furloughing of government workers and the closing of government facilities.

In nearly all government contracts, contractors have the right to recover increased costs caused by the government shutdown regardless of whether the specific government action was an express suspension of work order, an implied or express government delay, or a constructive change. This right of recovery, however, must be exercised quickly or else