New York State continues to advance its bulk energy storage
deployment efforts, and a final Bulk Storage Implementation Plan is
now likely to be made public before the end of April—with
procurements set to begin by June 30, 2025.
On Friday, March 21, the Public Service Commission
("PSC") approvedthe New York State Energy Research and
Development Authority's ("NYSERDA") draft Bulk Energy Storage Implementation Plan
Proposal (the "NYSERDA Proposal"), which was filed at the
PSC in October 2024.
We previously broke down the contents of the NYSERDA
Proposal in November 2024, the highlights of which include three
solicitations for 1,000 MW of storage capacity (planned to be held
in 2025, 2026, and 2027) and the creation of an Index Storage
Credit modeled on the extant REC and OREC approaches.