Government contractors often "flow down" contract
clauses from the Federal Acquisition Regulation (FAR) and its
supplements to their subcontractors, including clauses related to
changes (e.g., FAR 52.243-1) and excusable delays (e.g., FAR
52.249-14). As a result, subcontracts commonly provide that such
clauses should be interpreted consistent with the "federal
common law of government contracts," which generally includes
decisions by the U.S. Court of Appeals for the Federal Circuit, the
U.S. Court of Federal Claims, and the Civilian and Armed Services
Boards of Contract Appeals (CBCA and ASBCA).
A recent decision from the U.S. District Court for the Eastern
District of Virginia (EDVA) highlights the advantages and risks
that this arrangement presents. In particular, the federal common
law of government contracts includes multiple
"constructive" theories of
liability through which prime contractors can obtain additional
funds from the government. Incorporating