his month's bid protest spotlight focuses on one recent U.S. Court of Federal Claims decision and two U.S. Government Accountability Office decisions. While all three protests were unsuccessful...

United StatesGovernment, Public Sector

his month's bid protest spotlight focuses on one recent U.S. Court of Federal Claims decision and two U.S. Government Accountability Office decisions. While all three protests were unsuccessful, each serves as a different helpful reminder for contractors. The Court of Federal Claims decision is a reminder for those submitting proposals, while the two GAO decisions serve as reminders for unsuccessful offerors hoping to protest terms of a solicitation and award decisions.

The Bionetics Corp.

In The Bionetics Corp. v. U.S., the Court of Federal Claims denied Bionetics' protest that the U.S. Air Force impermissibly excluded Bionetics from competing for a multimillion-dollar contract award due to an error inBionetics'price proposal.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Morrison & Foerster LLP. All rights reserved

See more popular content from