Although there are often significant rewards associated with
transactions among government contractors, the transactions require
careful planning and coordination. Even then, there is a fair
amount of risk during the process: the novation process (when
required) is discretionary; the seller may have undisclosed
violations of procurement law; organizational conflicts of
interests may preclude the buyer from pursuing work; etc. We
previously wrote about corporate transactions as bases for protest
in our
Post-Award Protest Primer. The recent GAO decision in Wyle Labs reminds us that there is
also a risk to pending and future procurements. In Wyle,
GAO held that the agency could reasonably eliminate Wyle Labs from
a procurement when, because of a pending novation, the entity
actually proposed to perform was its subcontractor (and prospective
buyer of its OASIS contract), Grant Thornton.