GAO Finds That Challenge To Agency’s Failure To Comply With DFARS Requirement Comes Too Late

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

When government contractors believe solicitation terms conflict with statutes or regulations, they face a critical timing challenge that can make or break their ability to protest. A recent GAO decision demonstrates how waiting until discussions to raise concerns about RFP language can result in dismissal, even when the solicitation appears to contradict procurement law.

United StatesGovernment, Public Sector

GAO’s recent dismissal of the protest in Tyonek Technical Innovations, LLC, B-424364, B-424364.2, June 30, 2026, carries an important lesson for government contractors: if you believe solicitation terms conflict with a statute or regulation, you must raise that challenge before proposals are due—not during discussions or afterwards.

The protest arose from an Air Force small business set-aside procurement for cyber operations training support services. The RFP provided that an affiliate’s past performance would only be considered if the prime offeror demonstrated that the affiliate would perform “significant and critical aspects of the contract.” And the RFP warned offerors that absent the required documentation, “the proposed affiliate companies, sister companies, joint venture companies, etc. shall not be evaluated or considered.”

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from