On November 27, 2018, the U.S. Government Accountability Office
("GAO") released its Bid Protest Annual Report to Congress for Fiscal
Year 2018.
Under the Competition in Contracting Act of 1984
("CICA"), GAO is required to report annually to Congress
on each instance in which (1) a federal agency did not fully
implement a recommendation made by GAO in connection with a bid
protest decision, or (2) a final decision in a protest was not
rendered within 100 days after the date the protest was submitted
to the Comptroller General, during the prior fiscal year. GAO
reported no such instances for Fiscal Year 2018.
CICA also requires the Annual Report to include "a summary
of the most prevalent grounds for sustaining protests" during
the preceding fiscal year. For 2018, GAO reported the most
prevalent reasons for sustaining protests were: (1) an unreasonable
technical evaluation, (2) an unreasonable cost or price evaluation;
and (3) a flawed selection decision.