Clarifying a significant issue in government contracts
litigation against the government, the U.S. Court of Appeals for
the Federal Circuit has held that the so-called "sum
certain" requirement for Contract Disputes Act (CDA) claims
against the government is a nonjurisdictional rule, subject to
forfeiture if not timely raised by the government.
In its August 22, 2023, opinion in ECC International
Constructors, LLC v. Secretary of the Army (Fed. Cir. No.
21-2323), the court held that although contractors are required to
specify a "sum certain" (a specific dollar value sought)
when submitting monetary claims, their failure to do so does not
preclude a court or board from later reviewing the government's
decision on the contractor's claim. The court held, "We
conclude that Congress did not clearly state that a claim submitted
under the CDA must include a sum certain in order for the Board [of
Contract Appeals] or a court to exercise jurisdiction."