ARTICLE · 20 JANUARY 2025

Fast-Tracking Megaprojects: Balancing Speed, Feasibility, And Dispute Risks

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

President-elect Donald Trump has proposed to expedite federal approvals and permits for any investments worth more than $1 billion.

United StatesGovernment, Public Sector

What You Need to Know

  • Key takeaway #1

Fast-tracking risks: Accelerated permitting processes may lead to disputes due to insufficient stakeholder engagement, design oversights, and environmental impact issues.

  • Key takeaway #2

Findings from the World Bank report: Delays are more commonly driven by poor feasibility studies, weak procurement practices, and design flaws than by permitting issues alone.

  • Key takeaway #3

Lifecycle implications: Gaps in early project phases can result in significant litigation during execution, even for non-expedited projects.

  • Key takeaway #4

Dispute mitigation: Careful project planning, robust design processes, and proactive stakeholder engagement remain critical to minimizing disputes.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.