Since 1963, the federal government has relied on a doctrine
first advanced in G. L. Christian & Assocs. v. United
States to read certain terms and provisions into its contracts
despite the lack of any express reference thereto. This
"Christian doctrine" has been used to remedy
errors and omissions by contracting officials who fail to include
provisions satisfying two criteria: First, the provision must be
mandatory, and second, it must reflect a "significant or
deeply ingrained strand of public procurement policy."
Although this doctrine has historically had the effect of imposing
substantial costs and obligations on unsuspecting contractors after
the fact, the government's reliance on this doctrine has waned
in recent years. However, a recent decision from the U.S. Court of
Appeals for the Federal Circuit reaffirmed the doctrine's
relevance, demonstrating the need for contractors to continue
evaluating the completeness of their contracts.