Don't Wait: FAR Part 36 Offerors Must Protest Within 10 Days Of An Unsuccessful Offeror Notice

Federal contractors competing for architect-engineer and design-build contracts face a critical and often misunderstood timeliness trap that can doom their bid protests before they even begin.

United StatesGovernment, Public Sector

Companies competing in federal architect-engineer and design-build procurements under Federal Acquisition Regulation (FAR) Part 36 should be aware of a critical – and frequently misunderstood – timeliness requirement that can make or break a bid protest at the U.S. Government Accountability Office (GAO). Unlike procurements conducted under FAR Part 15, where a protest filed before an award has been made is premature and the protest clock is extended by a post-award debriefing, procurements conducted under FAR Subpart 36.6, Architect-Engineer (A/E) Services and FAR Subpart 36.3 (Two-Phase Design-Build Selection Procedures) have separate protest timeliness rules.

Because awards of FAR Subpart 36.6 procurements are not considered procurements "conducted on the basis of competitive proposals," if an unsuccessful offeror waits until after the agency publicly announces the awardee to file a protest, the protest will almost certainly be dismissed as untimely.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from