ARTICLE · 15 AUGUST 2025

Court Of Federal Claims Recognizes Additional Potential Recovery Opportunities Under Energy Savings Performance Contracts

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

Earlier this year, we highlighted a notable Court of Federal Claims (CFC) decision recognizing that an energy savings performance contract (ESPC)...

United StatesGovernment, Public Sector

Earlier this year, we highlighted a notable Court of Federal Claims (CFC) decision recognizing that an energy savings performance contract (ESPC) contractor may be able to recover proposal preparation costs under the CFC's bid protest jurisdiction. Now, in Siemens Government Technologies, Inc. v. United States, another CFC decision has reaches a similar conclusion and goes even further — also highlighting the potential to recover under the Court's Contract Disputes Act (CDA) jurisdiction.

In this case, Siemens contracted with the Department of Energy (DOE) under an indefinite delivery, indefinite quantity (IDIQ) ESPC. The ESPC included a clause providing that the government was not responsible for proposal preparation costs unless the government awarded a task order or an authorized contracting officer specifically approved payment of proposal preparation costs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from