Bid protest decisions of the Government Accountability Office
(GAO) and the U.S. Court of Federal Claims help shape the law of
how federal acquisition contracts should be awarded. What is often
overlooked, however, is that bid protest decisions can serve an
important secondary purpose. These cases frequently detail the
evaluation of contract proposals by federal agencies in best value
procurements and thus provide valuable guidance to contractors as
to what separates a successful proposal from an unsuccessful
proposal. A recent example of a protest decision offering such
insights is Infinity Systems Engineering, LLC, B-419043 2020 WL
9210680 (November 20, 2020). In this case, the GAO denied a protest
where it found the agency reasonably determined the disappointed
offeror did not meet the requirements of the solicitation.