The Court of Federal Claims issued a lengthy decision in a case arising from a construction project gone awry in which the contractor was terminated for default (T for D), ended up in bankruptcy, and lost a fraud counterclaim to DOJ.

United StatesGovernment, Public Sector

Tags: CFC, Firm Fixed-Price Contracts, Termination for Default

The Court of Federal Claims issued a lengthy decision in a case arising from a construction project gone awry in which the contractor was terminated for default (T for D), ended up in bankruptcy, and lost a fraud counterclaim to DOJ. The contractor had taken a substantial risk by agreeing to a firm-fixed price that was substantially lower than it had originally proposed—then (after a few problems) lacked the necessary liquidity to complete the project. The decision in Liquidating Trustee Ester Du Val of Ki Liquidation, Inc. v. US is a reminder that contractors agreeing to a firm-fixed price are accepting substantial risk, and when entering into this type of contract in unpredictable circumstances, they must be able to bear that risk, as a lifeline is unlikely to be forthcoming from the agency.