ARTICLE · 05 AUGUST 2025

A Greater Sum Of Certainty: ASBCA Weighs In On When Sum Certain Defense Is Not Waived

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

A recent Armed Services Board of Contract Appeals decision provides useful guidance on when the government may (or may not) waive its defense that a contractor's claim failed to state a sum certain.

United StatesGovernment, Public Sector

A recent Armed Services Board of Contract Appeals decision provides useful guidance on when the government may (or may not) waive its defense that a contractor's claim failed to state a sum certain. In GE Renewables US, LLC, the contractor had submitted a claim to the contracting officer for a determination that the contractor had the right to an economic price adjustment (EPA) due to an inflation-related price increase. Notably, the contractor did not provide the value of its requested adjustment in its claim. The contracting officer denied the claim, and the contractor appealed to the Board.

Just over two weeks before discovery was scheduled to close in the appeal, the government moved to dismiss for failure to claim a sum certain. The contractor challenged the timeliness of that motion. In ECC International Constructors, which we previously discussed, the Federal Circuit determined that the Federal Acquisition Regulations (FAR) requirement to include a sum

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from