Milbank has successfully represented the Official Committee of
Unsecured Creditors of FirstEnergy Solutions Corp.
(“FES”) and its affiliated debtors in their chapter 11
cases, which were filed in the Northern District of Ohio on March
31, 2018. FES is one of America’s largest utilities.
Headquartered in Akron, Ohio, FES operates one of the nation's
largest investor-owned electric systems, more than 24,000 miles of
transmission lines that connect the Midwest and Mid-Atlantic
regions, and a diverse generating fleet with a total capacity of
more than 16,000 megawatts.
As of December 31, 2017, FES listed $5.5 billion in total assets
against $1.25 billion in total current liabilities, $2.3 billion in
long-term debt and other long-term obligations and $4.0 billion in
non-current liabilities, consisting of sale and leaseback
obligations, retirement benefits and asset retirement
obligations.