Statutory Deadlines Matter — EPA Gets Taken To The Woodshed

EPA was ordered to take final action on a Clean Air Act § 126(b) petition filed by the State of Connecticut, asserting that emissions from the Brunner Island Steam Electric Station in Pennsylvania contribute to nonattainment in Connecticut.

United StatesEnvironment

Earlier this week, EPA was ordered to take final action on a Clean Air Act § 126(b) petition filed by the State of Connecticut, asserting that emissions from the Brunner Island Steam Electric Station in Pennsylvania contribute to nonattainment in Connecticut. EPA did not dispute liability; it had clearly missed the original statutory deadline. The case was all about the remedy. EPA asked to be given until December 31, 2018 to respond. Plaintiffs said EPA could respond within 60 days.

Noting the "heavy burden" EPA bears in trying to demonstrate that it cannot comply with the congressionally mandated timeline, The Court ordered a response within 60 days, concluding that:

Defendants' proposed schedule contravenes the congressional intent that EPA "act quickly on a Section 126(b) petition."