Share on LinkedInShare on LinkedIn

ARTICLE · 07 AUGUST 2023

Ohio Supreme Court Unanimously Affirms Siting Board Certificate For New Wind Farm

Dickinson Wright PLLC
Dickinson Wright PLLC
Contributor
Dickinson Wright PLLC

Dickinson Wright PLLC

Dickinson Wright is a full-service law firm with more than 550 lawyers, serving clients across the...

View firm profile
Explore more from Dickinson Wright PLLC

On July 27, 2023, the Supreme Court of Ohio, in a 7-0 decision, affirmed the Ohio Power Siting Board ("Board")'s decision to issue a certificate for environmental compatibility and public need ("Certificate")...

United StatesEnvironment

Emerson Creek project in Huron and Erie Counties Now Expected to Move to Construction

On July 27, 2023, the Supreme Court of Ohio, in a 7-0 decision, affirmed the Ohio Power Siting Board ("Board")'s decision to issue a certificate for environmental compatibility and public need ("Certificate") to construct the Emerson Creek Wind Farm, effectively authorizing Firelands Wind LLC ("Firelands") to proceed to construct the 297-megawatt wind-generation project in Huron and Erie counties.1 In a unanimous decision authored by Justice Pat DeWine, the Court found the Board did not act unlawfully or unreasonably when evaluating the wind farm's application and issuing a certificate to Firelands Wind.2

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.