EPA Proposes Rule To Redefine “Begin Actual Construction” Under The NSR Preconstruction Permitting Program

The EPA has proposed a significant revision to the Clean Air Act's New Source Review preconstruction permitting program that would allow companies to begin certain non-emitting construction activities before obtaining permits.

United StatesEnvironment

Key Takeaways

What Happened: The U.S. Environmental Protection Agency (EPA) recently proposed a new rule to revise the Clean Air Act’s (CAA) New Source Review (NSR) preconstruction permitting program to allow owners and operators to begin certain non-emitting construction activities before obtaining an NSR permit. Specifically, EPA proposes to:

  • Revise the definition of “begin actual construction”;
  • Add new definitions for the terms “pollutant-emitting activities” and “commence construction”; and
  • Make additional changes to clarify the distinction between the construction of a stationary source and the construction of non-emitting components or structures.

If finalized as proposed, EPA’s rule would allow companies (at their own risk) to perform certain non-emitting construction activities, such as building foundations, cement pads, and office buildings, before obtaining an NSR permit.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from