Recent regulatory developments are reshaping air quality permitting requirements for data centers and large infrastructure projects. EPA's proposed revisions to the New Source Review program, updated turbine emissions standards, and ongoing litigation signal a shifting landscape that could fundamentally alter how developers approach project sequencing and compliance obligations.

United StatesEnvironment

Three recent developments suggest that air quality permitting is becoming an increasingly central component of data center and other large infrastructure development. A proposed update to the U.S. Environmental Protection Agency (EPA)’s New Source Review (NSR) program; new emissions standards and categories for on-site power generation; and ongoing litigation over turbine use reflect an evolving regulatory dynamic that may shape the way projects are evaluated going forward.

Proposed NSR Revisions May Impact Project Sequencing

EPA has proposed a notable revision to the Clean Air Act’s (CAA) NSR program that could materially affect how data centers and other large infrastructure projects sequence construction and air permitting. In a May 2026 proposed rule, EPA seeks to revise the definition of “begin actual construction” and add a definition of “pollutant-emitting activities” to better distinguish between pollutant-emitting and non-emitting activities, allowing developers to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from