ARTICLE · 16 NOVEMBER 2021

Agreement To Extend Statute Of Limitations For CEQA Claim Was Ineffective Because It Did Not Include An Indispensable Party

The Court of Appeal held that a CEQA challenge to a decision approving removal of trees adjacent to PG&E gas pipelines was time-barred because an agreement to toll the statute of limitations did not include PG&E...

United StatesEnvironment

The Court of Appeal held that a CEQA challenge to a decision approving removal of trees adjacent to PG&E gas pipelines was time-barred because an agreement to toll the statute of limitations did not include PG&E, which was an indispensable party in the proceedings, and the suit was filed after the applicable 180-day limitations period had expired. Save Lafayette Trees v. East Bay Regional Park District (Pacific Gas and Electric Company), 66 Cal.App.5th 21 (2021).

As part of PG&E's Community Pipeline Safety Initiative, PG&E conducted an in-depth review of trees located near its gas transmission pipelines and identified a total of 245 trees in the East Bay Regional Park District that were located too close a pipeline. The District and PG&E agreed that the trees would be removed and that PG&E would fund the cost of removing the trees and installing replacement trees.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from