It may be 2020, but some big issues have carried over from the
last decade at the Public Utilities Commission of Ohio, including
the question of what the Commission will do to facilitate customer
and third-party access to AMI (or "smart meter")
electricity consumption data. As avid followers of the PUCO (all 14
of us) will remember, the state is heading toward near-universal
AMI rollout for most of its investor-owned utilities. Accordingly,
a key focus of the Commission's "PowerForward"
discussions beginning in 2017 was how to realize customer value
from Ohioans' investment in AMI meters.
The PUCO's 2018 PowerForward Roadmap ultimately recommended that
"standardized access to customer energy usage data (CEUD) for
CRES [competitive retail electric service] providers and other
third parties should be viewed as a fundamental and core component
of the [modern utility] platform," so that AMI data can
"be used to better enable customer choice to inform customers
of their