Share on LinkedInShare on LinkedIn

ARTICLE · 22 APRIL 2015

FERC Revises Interstate Natural Gas Pipeline Nomination Timelines

In the Final Rule, FERC retreated from certain changes it proposed in its April 1, 2014, Notice of Proposed Rulemaking (NOPR), which initiated this proceeding.

United StatesEnergy and Natural Resources

On April 16, 2015, the Federal Energy Regulatory Commission (FERC) issued a much-anticipated final rule modifying some of the scheduling practices used by interstate natural gas pipelines to better coordinate the scheduling of the wholesale natural gas and electricity markets (Order No. 809 or Final Rule).1 The Final Rule follows an extensive stakeholder process held by the North American Energy Standards Board (NAESB) involving the gas and electric industries, and multiple FERC technical conferences.

The core elements of Order No. 809 include:

  • Changing the nationwide Timely Nomination Cycle nomination deadline for scheduling natural gas transportation from 11:30 a.m. Central Clock Time (CCT) to 1:00 p.m. CCT

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from