FERC Rejects Grid Reliability And Resilience Pricing — For Now!

The intent of the proposal was to compensate generators who provide reliability and resilience attributes to the grid.

United StatesEnergy and Natural Resources

Yesterday, FERC terminated the docket it opened in response to DOE Secretary Perry's September proposal to compensate generators who maintain a 90-day fuel supply on-site.  The intent of the proposal was to compensate generators who provide reliability and resilience attributes to the grid.

The decision was unanimous, though there were several concurrences.  The commissioners were not persuaded that there is a reliability problem that requires immediate, out-of-market relief to coal and nuclear generators.

Neither the Proposed Rule nor the record in this proceeding has satisfied the threshold statutory requirement of demonstrating that the RTO/ISO tariffs are unjust and unreasonable. While some commenters allege grid resilience or reliability issues due to potential retirements of particular resources, we find that these assertions do not demonstrate the unjustness or unreasonableness of the existing RTO/ISO tariffs. In addition, the extensive