ARTICLE · 24 AUGUST 2016

FERC Eliminates Reactive Power Exemption For Wind Generators

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

FERC found in Order No. 827 that the existing exemption was unjust, unreasonable, and unduly discriminatory and preferential.

United StatesEnergy and Natural Resources

 On June 17, 2016, the Federal Energy Regulatory Commission ("FERC" or the "Commission") issued a final rule ("Order No. 827") eliminating exemptions for wind generators (and an option for solar generators to elect certain exemptions) from the requirement to provide reactive power. Unlike real power, which transfers net energy to the grid for use by consumers, reactive power is used for grid reliability, supporting voltages used for grid stability.

FERC requires that power generators design their systems to provide adequate amounts of reactive power to the transmission system to which they are interconnecting in order to maintain grid stability. Prior to the entry of Order No. 827, however, wind generators were exempted from the reactive power requirement, which required an interconnecting generator to design its generating facilities to have a reactive power capability of 0.95 leading to 0.95 lagging. This reactive power band essentially represents the range of