Share on LinkedInShare on LinkedIn

ARTICLE · 06 NOVEMBER 2015

FERC Denies Wind Generator Complaint Against MISO As Premature

On October 23, 2015, FERC issued an order denying a complaint brought by Merricourt Power Partners, LLC ("Merricourt") – which has been developing a 150 MW wind farm in North Dakota...

United StatesEnergy and Natural Resources

On October 23, 2015, FERC issued an order denying a complaint brought by Merricourt Power Partners, LLC ("Merricourt") – which has been developing a 150 MW wind farm in North Dakota – against the Midcontinent Independent System Operator, Inc. ("MISO") as premature. In the complaint, Merricourt sought an advanced determination that MISO would not terminate its Generator Interconnection Agreement ("GIA") even though it would not reach commercial operation within the three year period permitted under the GIA.

Under its tariff, MISO may terminate a GIA if the generating facility has failed to reach commercial operation in a three consecutive year period beginning on the original commercial operation date ("COD"). To terminate the GIA under these circumstances, MISO is required to give 90 days' advance written notice. The Merricourt GIA listed December 1, 2012 as the original COD. However, in its complaint, Merricourt conceded that it would fail to meet its original COD

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from