ARTICLE · 07 APRIL 2015

FERC Adopts New Regulations And Policies On Open Access And Priority Rights On Interconnection Customer Interconnection Facilities

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

On March 19, 2015, the Federal Energy Regulatory Commission (FERC or "Commission") issued Order No. 807.

United StatesEnergy and Natural Resources

On March 19, 2015, the Federal Energy Regulatory Commission (FERC or "Commission") issued Order No. 807 (the "Final Rule") that will provide owners and operators of Interconnection Customer Interconnection Facilities (ICIF) a blanket waiver of the Open Access Transmission Tariff requirements, the Open Access Same-Time Information System requirements, and the Standards of Conduct requirements (collectively, the "OATT Requirements"), subject to certain conditions.

The Final Rule and related changes in FERC's regulations are significant for many market participants, including developers planning new generation and interconnection facilities, prospective wholesale power sellers seeking market-based rate authorization to sell power from new facilities, and owners and operators of existing electric generation and interconnection facilities (including parties to negotiated agreements for shared use of generator tie-lines and other interconnection facilities that provide