FERC's Generator Interconnection Technical Conference Elicits Debate On Need For Interconnection Process Reforms

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

Panel 1 explored the causes of interconnection queue delays and potential methods of mitigating such delays.

United StatesEnergy and Natural Resources

On May 13, 2016, the Federal Energy Regulatory Commission (FERC or the "Commission") held a technical conference on generator interconnection issues in partial response to a June 2015 Petition filed by the American Wind Energy Association requesting a formal rulemaking to revise FERC's pro forma Large Generator Interconnection Procedures and Large Generator Interconnection Agreement.

During the daylong conference,1 representatives from Regional Transmission Organizations and Independent System Operators (RTOs/ISOs), generation project developers, investor-owned utilities, transmission owners and independent power producers (IPPs) covered topics including: (1) generator interconnection queue management and performance metrics and the causes of, and mitigation options, for backlogs; (2) transparency and timing in interconnection study processes, including restudy triggers; (3) certainty in cost and construction time estimates; (4) queue coordination and management

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.