How Immediate Is "Prompt" In A Contract? New Delaware Supreme Court Justice Vaughan Finds That It Depends

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

What does the term "prompt" mean in a contract? Well, it depends, according to Judge James T. Vaughn Jr., who was recently confirmed to the Delaware Supreme Court.

United StatesCorporate/Commercial Law

What does the term "prompt" mean in a contract? Well, it depends, according to Judge James T. Vaughn Jr., who was recently confirmed to the Delaware Supreme Court. In an opinion issued last week from his prior post in the Superior Court (Complex Commercial Division), Justice Vaughan found that notice after ten months may in some circumstances constitute "prompt notice."

In Avaya, Inc. v. Charter Communications Holding Company, LLC, C.A. No. N14C-03-052, Plaintiff Avaya, Inc. ("Avaya") moved for summary judgment, arguing that defendants Charter Communications Holding Company, LLC and Charter Communications, Inc. (together "Charter") failed to satisfy a contractual indemnity requirement to "promptly notify" Avaya of a claim or suit for which indemnity was requested. Charter was served with the complaint at issue on September 5, 2006. However, Charter did not provide a copy of that complaint and tender its defense to Avaya until approximately ten months later on July