NEC4 has now been launched and the authors have promised "evolution not revolution". NEC have based the changes on industry feedback and step changes in delivery methods.

United KingdomReal Estate and Construction

NEC4 has now been launched and the authors have promised "evolution not revolution". NEC have based the changes on industry feedback and step changes in delivery methods.

In this article, we review the main changes and what you need to know. The NEC4 drafting team has confirmed (as users would anticipate) that an overarching consideration has been to seek to reduce the number of Z clauses incorporated by users and so produce a more streamlined contract.

NEC4 - what are the key changes to the core clauses?

  1. Programme - core wording now provides for deemed acceptance of the contractor's programme if the project manager (PM) fails to respond within the prescribed timescales.