It's Just A Phase… Isn't It?

The community infrastructure levy ("CIL") is payable on chargeable developments. Where a planning permission is expressly stated to be phased...

United KingdomReal Estate and Construction

The recent judgment of the High Court in the Oval Estates case has highlighted the importance to developers in settling CIL phasing strategies early on in the planning process and not relying on retrospective action.

The community infrastructure levy (“CIL”) is payable on chargeable developments. Where a planning permission is expressly stated to be phased, each phase of the development is treated as a separate chargeable development for CIL purposes, meaning the CIL bill can be broken down into smaller payments.

In this case, on 2 March 2016, the charging authority granted outline permission for a residential development. The planning permission wasn’t phased.

The reserved matters consent, granted on 6 April 2017, approved a drawing which identified three phases of development.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from