Introduction
In 2010 I ventured a general article on construction
contractors' overheads claims ("FM1")
1Mastrandrea,
F, The Evaluation of Contractors' Overheads Claims in
Construction, [2010] The International Construction Law
Review, 299.
This article
2For a more
comprehensive review of this topic, see Mastrandrea, F, Does
the Hudson formula have a future? , to be published in (2024)
Const. L.J. Issue 3.
briefly revisits a limited area covered in FM1, namely one of the
appraisal methods for overheads claims which appears first to have
been formally set down in Hudson, Building and Engineering
Contracts, Sweet & Maxwell, 10th Edition, 1970,
at page 599, whose editor Mr. Duncan Wallace described it as the
formula 'usually used' by contractors for the
purposes of assessing the loss due to delay in completion,
thenceforth labelled "the Hudson formula"
3The formula
is: HO % in Contract Sum/100 x Contract Sum/Contract Period x
Period of