Today's entry looks at the Government's new statistics on major projects, a court case on highways impacts, and how the new NPPF is being applied.
Baby Steps
The Planning Inspectorate has published its usual interesting data on nationally significant infrastructure projects. The statistics show that the average length of the pre-application period was 2.4 years in 2024, 2.03 years in 2025, and rose in 2026 to 2.58 years. Meanwhile examinations have seen some improvement (5.74 months in 2024, down to 5.31 months in 2026). Recommendations have risen (2.84 months in 2024 vs. 2.95 months in 2026). So it's a case of right, left, baby steps.
There is a significant limitation in the pre-application statistics: that period is "defined as the time from the inception meeting date to the date of application submission". Most developers, however, have been going at things for a period of time before the inception meeting, and most wise developers will time their inception meeting to reduce