Delivering major development is difficult. One of the deterrents is often the need to assemble fragmented land ownerships.

United KingdomReal Estate and Construction

Delivering major development is difficult. One of the deterrents is often the need to assemble fragmented land ownerships. The availability of compulsory purchase powers is critically important to give developers some certainty that they will be able to deliver. The powers should be available and should be used more widely.

However, CPOs should only be used as a last resort. In some recent cases there appears to have been a move to treat negotiations and voluntary deals as an irritant rather than a requirement. For example:

  • some CPOs are being made before any real approach to significant affected landowners by either the Council and/or the developer. Even if a CPO is inevitable, an early approach to those affected should be a pre-condition of the Order being made;