Failing to agree clear terms in advance of starting work is a clear risk, as most recently shown in the Technology and Construction Court (TCC) judgment in Changing Climates Ltd v Warmaway Ltd [2021].

United KingdomReal Estate and Construction

Failing to agree clear terms in advance of starting work is a clear risk, as most recently shown in the Technology and Construction Court (TCC) judgment in Changing Climates Ltd v Warmaway Ltd [2021]. These proceedings related to an application for summary judgment to enforce an adjudication decision. The jurisdiction of the adjudicator had been challenged by Warmaway, with the contention being that there was no contract at all in place between Warmaway and Changing Climates (CC).

If Warmaway was correct, there could be no "construction contract" between the parties as defined in the Housing Grants, Construction and Regeneration Act 1996 as amended (the Construction Act), meaning that there was no right to adjudication and the adjudicator would not have jurisdiction in respect of the dispute.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from