TTSJV sought an injunction to require BapCo to suspend its demand on a performance guarantee issued by HSBC Bank Middle East Ltd (in the sum of US$484,406,323) and to restrain BapCo from making any further demand pending further order of the court or of any emergency arbitrator that might be appointed by the LCIA.
BapCo had entered into an EPC contract with TTSJV, a consortium of companies from the USA, Italy, Spain and the Republic of Korea, to complete a modernisation programme to upgrade BapCo’s existing oil refinery in Bahrain. The contract was governed by the laws of England and Wales. Any dispute was to be referred to binding arbitration under the LCIA Rules, with the seat of the arbitration being London.