In a recent landmark case, the Court has upheld an arbitration
award providing for the recovery of third party funding costs. We
discuss the case and the repercussions for traders today.
The Court, in Essar Oilfield Services Ltd v Norscot Rig
Management Pvt Ltd [2016] EWHC (Comm) 2361 (judgment handed down on
15 September 2016), dismissed an application brought by Essar
against an arbitral award that provided for the recovery of
Norscot's finance costs in obtaining third party funding.
Norscot commenced London-seated ICC proceedings against Essar
for repudiatory breach of an operations management agreement and
entered into a financing arrangement with a litigation funder to
bring the claim. Norscot was successful in the arbitration and
sought its legal fees and the costs of the finance of those fees.
The third-party funding consisted of an advance of GBP 647,086 with
repayment to be the greater of 300% of the sum advanced or 35% of
the damages awarded.